Punta Pool Area Update
December 23, 2012
The Punta Pools have water in them and planting is proceeding at a fevorish pace. Although management's goal of December 15 has come and gone, the team members are very close to meeting their goal. Only 10 days off. The Punta Pools are said to open on December 25, 2012 at 7 AM.Gordon's son was able to take a few photos of the Punta Pool area. It is quite a difference from last March! Very beautiful and plenty of lake area. What do you think?
Here is the progression:
July 10, 2012 - GSnider
August 27, 2012 - Gary III
Plugin Image
File not found.
Plugin Image
File not found.
Plugin Image
File not found.
November 16, 2012 - Bob and Mary Ann
December 18, 2012 - Linda in Seattle
December 23, 2012 - Gordon's Son
Wow! A huge amount of work in a relatively short period of time - baiscally August to December.
Thank you GSnider for your most recent photos of a functioning Punta Pool area, and thank you Gary III for alerting us to the beginning of the change.
Managment did a great job of finishing close to their self imposed estimates. The transformation is incredible. Certainly a smaller footprint, don't you think? But will the pools be heated?